BitRoads will begin work on Monday, June 27th starting at 7 AM.
Please make sure residents have their cars cleared from garages and driveways on Wescott Trail by this time.
Wescott Trail garages should be left open by that time and my crew will shut them when they’re done with the area. They can also pull the release so my crew can open and shut them as needed.
Garbage on Wescott Trail will be cancelled. Residents can wait for a week, or bring the barrels to Wescott Square.
I will post signs on the driveways that will be affected that specific day but if you want to make it a blanket statement for all tenants feel free to do that.
We will be core filling on an as needed basis at a price of $700 per driveway that gets filled.
If we experience any poor subsoils beneath the asphalt, we will reach out to Pierre to observe and decide whether you would like us to sub-cut and install new rock. This will be charged at $55/Cubic Yard. One truckload is 10 cubic yards.
We will be removing concrete pads/tree roots that backflow into the stairs to help make sure water will not be trapped.
Monday and Tuesday will be excavation and grading to prepare for paving. Wednesday-Friday we will be paving the driveways. I will adjust my signs for the paving, so they have appropriate verbiage.
Please avoid any long-term parking on the new driveways for at least one week. Even longer would be preferred. We will not be responsible for any rutting or damages that may occur if heavy vehicles are parked on the new asphalt for a long time too quickly after paving. Tenants may drive over the asphalt and pull directly into their garage 24 hours after paving is completed.
We will coordinate with Pierre for any towing needs that we might have. Please let me know if you have any questions or concerns otherwise we should be good to go!
The above repaving is for Wescott Trail driveways only. Wescott Trail will be scheduled for resurfacing in Mid-August 2022. Another announcement will be made available at a later date.